Representative Work: Lien Claim
We represented a local supplier with a construction lien claim against the largest private construction project in Oregon in 2012. Our client's customer, a large subcontractor on the project, walked off the project due to a change order and other disputes with the general contractor. The subcontractor owed our client a significant sum for materials which related in part to the disputed change order and extra work claims. We prepared and recorded a lien against the project and then successfully negotiated payment with counsel for the general contractor. Our client received full payment without filing a lawsuit and avoided the fallout and delay of the ensuing lawsuit between the general contractor and our client's customer.